Construction at Eden Residences continues to progress, with interior finishing advancing across Buildings C, D, E, F, and G. Third-floor window installations are complete, while tiling and air conditioning works are underway. Engineering systems are being installed in Building B, Building A has reached third-floor structural works, and foundation construction continues at the Lobby building.
Construction at Eden Residences continues to advance, with structural and masonry works fully completed in Building B. Interior finishing is progressing across Buildings C, D, E, F, and G, including window installations, engineering systems, and floor screeding on the third floor. Building A has entered the next structural stage, while piling works have commenced for the Lobby building.
Construction at Eden Residences has reached another milestone, with Buildings C, D, E, F, and G now at their full structural height. Interior finishing of the first residences is underway, with tiling, ceilings, and air conditioning installations completed on the first floor. Building B has also reached its full height, while Building A has progressed to first-floor slab construction.
Construction at Eden Residences continues to advance, with increasing focus on interior finishing. Window installations, floor screeding, ceiling works, and tiling have progressed across Buildings C, D, E, F, and G. Building B has moved into architectural works, with masonry reaching the second floor, while Building A has completed its foundation stage and commenced construction of the first-floor slab.
Construction at Eden Residences continues to progress across all buildings. Plastering on the second and third floors and floor screeding on the first floor have been completed in Buildings C, D, E, F, and G. Engineering installations and interior finishing works are advancing, while Building B has reached roof slab completion and foundation works continue in Building A.
Construction at Eden Residences continues to advance. Internal and external walls have reached the fourth floor across Buildings C, D, E, F, and G, with plumbing and electrical installations completed up to the third floor. Structural works are progressing in Building B, while piling works in Building A are 95% complete.
Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage.
The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards.
At Eden Residences, first-floor wall structures are complete across most buildings, with second-floor masonry now actively progressing. Installation of sanitary systems has begun using advanced three-layer silent drainage pipes, ensuring higher comfort for future residents.
The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building.
The latest construction progress across Gardens of Eden — everything is on track and built to the highest standards.
The beachfront phase is moving into the final structural stages — with roof slabs completed and wall construction underway across all buildings.