施工更新
Eden Residences

施工更新

项目进度

Environmental Impact Assessment Construction Permit

预计于 2026年12月31日 竣工

90%

Construction at Eden Residences continues to progress, with interior finishing advancing across Buildings C, D, E, F, and G. Third-floor window installations are complete, while tiling and air conditioning works are underway. Engineering systems are being installed in Building B, Building A has reached third-floor structural works, and foundation construction continues at the Lobby building.

Construction at Eden Residences continues to progress, with interior finishing advancing across Buildings C, D, E, F, and G. Third-floor window installations are complete, while tiling and air conditioning works are underway. Engineering systems are being installed in Building B, Building A has reached third-floor structural works, and foundation construction continues at the Lobby building. - image 1Construction at Eden Residences continues to progress, with interior finishing advancing across Buildings C, D, E, F, and G. Third-floor window installations are complete, while tiling and air conditioning works are underway. Engineering systems are being installed in Building B, Building A has reached third-floor structural works, and foundation construction continues at the Lobby building. - image 2Construction at Eden Residences continues to progress, with interior finishing advancing across Buildings C, D, E, F, and G. Third-floor window installations are complete, while tiling and air conditioning works are underway. Engineering systems are being installed in Building B, Building A has reached third-floor structural works, and foundation construction continues at the Lobby building. - image 3Construction at Eden Residences continues to progress, with interior finishing advancing across Buildings C, D, E, F, and G. Third-floor window installations are complete, while tiling and air conditioning works are underway. Engineering systems are being installed in Building B, Building A has reached third-floor structural works, and foundation construction continues at the Lobby building. - image 4Construction at Eden Residences continues to progress, with interior finishing advancing across Buildings C, D, E, F, and G. Third-floor window installations are complete, while tiling and air conditioning works are underway. Engineering systems are being installed in Building B, Building A has reached third-floor structural works, and foundation construction continues at the Lobby building. - image 5Construction at Eden Residences continues to progress, with interior finishing advancing across Buildings C, D, E, F, and G. Third-floor window installations are complete, while tiling and air conditioning works are underway. Engineering systems are being installed in Building B, Building A has reached third-floor structural works, and foundation construction continues at the Lobby building. - image 6Construction at Eden Residences continues to progress, with interior finishing advancing across Buildings C, D, E, F, and G. Third-floor window installations are complete, while tiling and air conditioning works are underway. Engineering systems are being installed in Building B, Building A has reached third-floor structural works, and foundation construction continues at the Lobby building. - image 7
观看完整更新

Construction at Eden Residences continues to advance, with structural and masonry works fully completed in Building B. Interior finishing is progressing across Buildings C, D, E, F, and G, including window installations, engineering systems, and floor screeding on the third floor. Building A has entered the next structural stage, while piling works have commenced for the Lobby building.

Construction at Eden Residences continues to advance, with structural and masonry works fully completed in Building B. Interior finishing is progressing across Buildings C, D, E, F, and G, including window installations, engineering systems, and floor screeding on the third floor. Building A has entered the next structural stage, while piling works have commenced for the Lobby building. - image 1Construction at Eden Residences continues to advance, with structural and masonry works fully completed in Building B. Interior finishing is progressing across Buildings C, D, E, F, and G, including window installations, engineering systems, and floor screeding on the third floor. Building A has entered the next structural stage, while piling works have commenced for the Lobby building. - image 2Construction at Eden Residences continues to advance, with structural and masonry works fully completed in Building B. Interior finishing is progressing across Buildings C, D, E, F, and G, including window installations, engineering systems, and floor screeding on the third floor. Building A has entered the next structural stage, while piling works have commenced for the Lobby building. - image 3Construction at Eden Residences continues to advance, with structural and masonry works fully completed in Building B. Interior finishing is progressing across Buildings C, D, E, F, and G, including window installations, engineering systems, and floor screeding on the third floor. Building A has entered the next structural stage, while piling works have commenced for the Lobby building. - image 4Construction at Eden Residences continues to advance, with structural and masonry works fully completed in Building B. Interior finishing is progressing across Buildings C, D, E, F, and G, including window installations, engineering systems, and floor screeding on the third floor. Building A has entered the next structural stage, while piling works have commenced for the Lobby building. - image 5Construction at Eden Residences continues to advance, with structural and masonry works fully completed in Building B. Interior finishing is progressing across Buildings C, D, E, F, and G, including window installations, engineering systems, and floor screeding on the third floor. Building A has entered the next structural stage, while piling works have commenced for the Lobby building. - image 6
观看完整更新

Construction at Eden Residences has reached another milestone, with Buildings C, D, E, F, and G now at their full structural height. Interior finishing of the first residences is underway, with tiling, ceilings, and air conditioning installations completed on the first floor. Building B has also reached its full height, while Building A has progressed to first-floor slab construction.

Construction at Eden Residences has reached another milestone, with Buildings C, D, E, F, and G now at their full structural height. Interior finishing of the first residences is underway, with tiling, ceilings, and air conditioning installations completed on the first floor. Building B has also reached its full height, while Building A has progressed to first-floor slab construction. - image 1Construction at Eden Residences has reached another milestone, with Buildings C, D, E, F, and G now at their full structural height. Interior finishing of the first residences is underway, with tiling, ceilings, and air conditioning installations completed on the first floor. Building B has also reached its full height, while Building A has progressed to first-floor slab construction. - image 2Construction at Eden Residences has reached another milestone, with Buildings C, D, E, F, and G now at their full structural height. Interior finishing of the first residences is underway, with tiling, ceilings, and air conditioning installations completed on the first floor. Building B has also reached its full height, while Building A has progressed to first-floor slab construction. - image 3Construction at Eden Residences has reached another milestone, with Buildings C, D, E, F, and G now at their full structural height. Interior finishing of the first residences is underway, with tiling, ceilings, and air conditioning installations completed on the first floor. Building B has also reached its full height, while Building A has progressed to first-floor slab construction. - image 4Construction at Eden Residences has reached another milestone, with Buildings C, D, E, F, and G now at their full structural height. Interior finishing of the first residences is underway, with tiling, ceilings, and air conditioning installations completed on the first floor. Building B has also reached its full height, while Building A has progressed to first-floor slab construction. - image 5Construction at Eden Residences has reached another milestone, with Buildings C, D, E, F, and G now at their full structural height. Interior finishing of the first residences is underway, with tiling, ceilings, and air conditioning installations completed on the first floor. Building B has also reached its full height, while Building A has progressed to first-floor slab construction. - image 6
观看完整更新

Construction at Eden Residences continues to advance, with increasing focus on interior finishing. Window installations, floor screeding, ceiling works, and tiling have progressed across Buildings C, D, E, F, and G. Building B has moved into architectural works, with masonry reaching the second floor, while Building A has completed its foundation stage and commenced construction of the first-floor slab.

Construction at Eden Residences continues to advance, with increasing focus on interior finishing. Window installations, floor screeding, ceiling works, and tiling have progressed across Buildings C, D, E, F, and G. Building B has moved into architectural works, with masonry reaching the second floor, while Building A has completed its foundation stage and commenced construction of the first-floor slab. - image 1Construction at Eden Residences continues to advance, with increasing focus on interior finishing. Window installations, floor screeding, ceiling works, and tiling have progressed across Buildings C, D, E, F, and G. Building B has moved into architectural works, with masonry reaching the second floor, while Building A has completed its foundation stage and commenced construction of the first-floor slab. - image 2Construction at Eden Residences continues to advance, with increasing focus on interior finishing. Window installations, floor screeding, ceiling works, and tiling have progressed across Buildings C, D, E, F, and G. Building B has moved into architectural works, with masonry reaching the second floor, while Building A has completed its foundation stage and commenced construction of the first-floor slab. - image 3Construction at Eden Residences continues to advance, with increasing focus on interior finishing. Window installations, floor screeding, ceiling works, and tiling have progressed across Buildings C, D, E, F, and G. Building B has moved into architectural works, with masonry reaching the second floor, while Building A has completed its foundation stage and commenced construction of the first-floor slab. - image 4Construction at Eden Residences continues to advance, with increasing focus on interior finishing. Window installations, floor screeding, ceiling works, and tiling have progressed across Buildings C, D, E, F, and G. Building B has moved into architectural works, with masonry reaching the second floor, while Building A has completed its foundation stage and commenced construction of the first-floor slab. - image 5Construction at Eden Residences continues to advance, with increasing focus on interior finishing. Window installations, floor screeding, ceiling works, and tiling have progressed across Buildings C, D, E, F, and G. Building B has moved into architectural works, with masonry reaching the second floor, while Building A has completed its foundation stage and commenced construction of the first-floor slab. - image 6Construction at Eden Residences continues to advance, with increasing focus on interior finishing. Window installations, floor screeding, ceiling works, and tiling have progressed across Buildings C, D, E, F, and G. Building B has moved into architectural works, with masonry reaching the second floor, while Building A has completed its foundation stage and commenced construction of the first-floor slab. - image 7
观看完整更新

Construction at Eden Residences continues to progress across all buildings. Plastering on the second and third floors and floor screeding on the first floor have been completed in Buildings C, D, E, F, and G. Engineering installations and interior finishing works are advancing, while Building B has reached roof slab completion and foundation works continue in Building A.

Construction at Eden Residences continues to progress across all buildings. Plastering on the second and third floors and floor screeding on the first floor have been completed in Buildings C, D, E, F, and G. Engineering installations and interior finishing works are advancing, while Building B has reached roof slab completion and foundation works continue in Building A. - image 1Construction at Eden Residences continues to progress across all buildings. Plastering on the second and third floors and floor screeding on the first floor have been completed in Buildings C, D, E, F, and G. Engineering installations and interior finishing works are advancing, while Building B has reached roof slab completion and foundation works continue in Building A. - image 2Construction at Eden Residences continues to progress across all buildings. Plastering on the second and third floors and floor screeding on the first floor have been completed in Buildings C, D, E, F, and G. Engineering installations and interior finishing works are advancing, while Building B has reached roof slab completion and foundation works continue in Building A. - image 3Construction at Eden Residences continues to progress across all buildings. Plastering on the second and third floors and floor screeding on the first floor have been completed in Buildings C, D, E, F, and G. Engineering installations and interior finishing works are advancing, while Building B has reached roof slab completion and foundation works continue in Building A. - image 4Construction at Eden Residences continues to progress across all buildings. Plastering on the second and third floors and floor screeding on the first floor have been completed in Buildings C, D, E, F, and G. Engineering installations and interior finishing works are advancing, while Building B has reached roof slab completion and foundation works continue in Building A. - image 5
观看完整更新

Construction at Eden Residences continues to advance. Internal and external walls have reached the fourth floor across Buildings C, D, E, F, and G, with plumbing and electrical installations completed up to the third floor. Structural works are progressing in Building B, while piling works in Building A are 95% complete.

Construction at Eden Residences continues to advance. Internal and external walls have reached the fourth floor across Buildings C, D, E, F, and G, with plumbing and electrical installations completed up to the third floor. Structural works are progressing in Building B, while piling works in Building A are 95% complete. - image 1Construction at Eden Residences continues to advance. Internal and external walls have reached the fourth floor across Buildings C, D, E, F, and G, with plumbing and electrical installations completed up to the third floor. Structural works are progressing in Building B, while piling works in Building A are 95% complete. - image 2Construction at Eden Residences continues to advance. Internal and external walls have reached the fourth floor across Buildings C, D, E, F, and G, with plumbing and electrical installations completed up to the third floor. Structural works are progressing in Building B, while piling works in Building A are 95% complete. - image 3Construction at Eden Residences continues to advance. Internal and external walls have reached the fourth floor across Buildings C, D, E, F, and G, with plumbing and electrical installations completed up to the third floor. Structural works are progressing in Building B, while piling works in Building A are 95% complete. - image 4
观看完整更新

Gardens of Eden construction continues in steady sequences. At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage.

Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 1Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 2Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 3Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 4Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 5Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 6Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 7Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 8Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 9Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 10Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 11Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 12Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 13Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 14Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 15Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 16Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 17Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 18Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 19Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 20Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 21
观看完整更新

The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. At Eden Residences, first-floor wall structures are complete across most buildings, with second-floor masonry now actively progressing. Installation of sanitary systems has begun using advanced three-layer silent drainage pipes, ensuring higher comfort for future residents.

The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards.
At Eden Residences, first-floor wall structures are complete across most buildings, with second-floor masonry now actively progressing. Installation of sanitary systems has begun using advanced three-layer silent drainage pipes, ensuring higher comfort for future residents. - image 1The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards.
At Eden Residences, first-floor wall structures are complete across most buildings, with second-floor masonry now actively progressing. Installation of sanitary systems has begun using advanced three-layer silent drainage pipes, ensuring higher comfort for future residents. - image 2The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards.
At Eden Residences, first-floor wall structures are complete across most buildings, with second-floor masonry now actively progressing. Installation of sanitary systems has begun using advanced three-layer silent drainage pipes, ensuring higher comfort for future residents. - image 3The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards.
At Eden Residences, first-floor wall structures are complete across most buildings, with second-floor masonry now actively progressing. Installation of sanitary systems has begun using advanced three-layer silent drainage pipes, ensuring higher comfort for future residents. - image 4The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards.
At Eden Residences, first-floor wall structures are complete across most buildings, with second-floor masonry now actively progressing. Installation of sanitary systems has begun using advanced three-layer silent drainage pipes, ensuring higher comfort for future residents. - image 5The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards.
At Eden Residences, first-floor wall structures are complete across most buildings, with second-floor masonry now actively progressing. Installation of sanitary systems has begun using advanced three-layer silent drainage pipes, ensuring higher comfort for future residents. - image 6The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards.
At Eden Residences, first-floor wall structures are complete across most buildings, with second-floor masonry now actively progressing. Installation of sanitary systems has begun using advanced three-layer silent drainage pipes, ensuring higher comfort for future residents. - image 7The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards.
At Eden Residences, first-floor wall structures are complete across most buildings, with second-floor masonry now actively progressing. Installation of sanitary systems has begun using advanced three-layer silent drainage pipes, ensuring higher comfort for future residents. - image 8
观看完整更新

The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building.

The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building. - image 1The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building. - image 2The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building. - image 3The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building. - image 4The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building. - image 5The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building. - image 6The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building. - image 7The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building. - image 8The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building. - image 9The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building. - image 10The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building. - image 11The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building. - image 12The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building. - image 13The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building. - image 14
观看完整更新

The latest construction progress across Gardens of Eden — everything is on track and built to the highest standards. The beachfront phase is moving into the final structural stages — with roof slabs completed and wall construction underway across all buildings.

The latest construction progress across Gardens of Eden — everything is on track and built to the highest standards.
The beachfront phase is moving into the final structural stages — with roof slabs completed and wall construction underway across all buildings. - image 1The latest construction progress across Gardens of Eden — everything is on track and built to the highest standards.
The beachfront phase is moving into the final structural stages — with roof slabs completed and wall construction underway across all buildings. - image 2The latest construction progress across Gardens of Eden — everything is on track and built to the highest standards.
The beachfront phase is moving into the final structural stages — with roof slabs completed and wall construction underway across all buildings. - image 3The latest construction progress across Gardens of Eden — everything is on track and built to the highest standards.
The beachfront phase is moving into the final structural stages — with roof slabs completed and wall construction underway across all buildings. - image 4The latest construction progress across Gardens of Eden — everything is on track and built to the highest standards.
The beachfront phase is moving into the final structural stages — with roof slabs completed and wall construction underway across all buildings. - image 5The latest construction progress across Gardens of Eden — everything is on track and built to the highest standards.
The beachfront phase is moving into the final structural stages — with roof slabs completed and wall construction underway across all buildings. - image 6
观看完整更新