项目进度

Environmental Impact Assessment Construction Permit

预计于 2026年12月31日 竣工

74%

Gardens of Eden construction continues in steady sequences. At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage.

Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 1Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 2Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 3Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 4Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 5Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 6Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 7Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 8Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 9Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 10Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 11Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 12Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 13Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 14Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 15Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 16Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 17Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 18Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 19Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 20Gardens of Eden construction continues in steady sequences.
At Eden Residences, masonry is finished in Buildings C and E, and progressing on the upper floors of G, D, and F. Plumbing and electrical installations have moved beyond the first floors, marking the next stage. - image 21

The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. At Eden Residences, first-floor wall structures are complete across most buildings, with second-floor masonry now actively progressing. Installation of sanitary systems has begun using advanced three-layer silent drainage pipes, ensuring higher comfort for future residents.

The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards.
At Eden Residences, first-floor wall structures are complete across most buildings, with second-floor masonry now actively progressing. Installation of sanitary systems has begun using advanced three-layer silent drainage pipes, ensuring higher comfort for future residents. - image 1The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards.
At Eden Residences, first-floor wall structures are complete across most buildings, with second-floor masonry now actively progressing. Installation of sanitary systems has begun using advanced three-layer silent drainage pipes, ensuring higher comfort for future residents. - image 2The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards.
At Eden Residences, first-floor wall structures are complete across most buildings, with second-floor masonry now actively progressing. Installation of sanitary systems has begun using advanced three-layer silent drainage pipes, ensuring higher comfort for future residents. - image 3The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards.
At Eden Residences, first-floor wall structures are complete across most buildings, with second-floor masonry now actively progressing. Installation of sanitary systems has begun using advanced three-layer silent drainage pipes, ensuring higher comfort for future residents. - image 4The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards.
At Eden Residences, first-floor wall structures are complete across most buildings, with second-floor masonry now actively progressing. Installation of sanitary systems has begun using advanced three-layer silent drainage pipes, ensuring higher comfort for future residents. - image 5The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards.
At Eden Residences, first-floor wall structures are complete across most buildings, with second-floor masonry now actively progressing. Installation of sanitary systems has begun using advanced three-layer silent drainage pipes, ensuring higher comfort for future residents. - image 6The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards.
At Eden Residences, first-floor wall structures are complete across most buildings, with second-floor masonry now actively progressing. Installation of sanitary systems has begun using advanced three-layer silent drainage pipes, ensuring higher comfort for future residents. - image 7The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards.
At Eden Residences, first-floor wall structures are complete across most buildings, with second-floor masonry now actively progressing. Installation of sanitary systems has begun using advanced three-layer silent drainage pipes, ensuring higher comfort for future residents. - image 8

The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building.

The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building. - image 1The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building. - image 2The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building. - image 3The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building. - image 4The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building. - image 5The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building. - image 6The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building. - image 7The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building. - image 8The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building. - image 9The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building. - image 10The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building. - image 11The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building. - image 12The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building. - image 13The latest construction progress across Gardens of Eden — everything remains on schedule and built to the highest standards. Eden Residences is moving confidently through the next phase: all reinforced concrete structures are complete, and wall construction is actively progressing across every building. - image 14

The latest construction progress across Gardens of Eden — everything is on track and built to the highest standards. The beachfront phase is moving into the final structural stages — with roof slabs completed and wall construction underway across all buildings.

The latest construction progress across Gardens of Eden — everything is on track and built to the highest standards.
The beachfront phase is moving into the final structural stages — with roof slabs completed and wall construction underway across all buildings. - image 1The latest construction progress across Gardens of Eden — everything is on track and built to the highest standards.
The beachfront phase is moving into the final structural stages — with roof slabs completed and wall construction underway across all buildings. - image 2The latest construction progress across Gardens of Eden — everything is on track and built to the highest standards.
The beachfront phase is moving into the final structural stages — with roof slabs completed and wall construction underway across all buildings. - image 3The latest construction progress across Gardens of Eden — everything is on track and built to the highest standards.
The beachfront phase is moving into the final structural stages — with roof slabs completed and wall construction underway across all buildings. - image 4The latest construction progress across Gardens of Eden — everything is on track and built to the highest standards.
The beachfront phase is moving into the final structural stages — with roof slabs completed and wall construction underway across all buildings. - image 5The latest construction progress across Gardens of Eden — everything is on track and built to the highest standards.
The beachfront phase is moving into the final structural stages — with roof slabs completed and wall construction underway across all buildings. - image 6